OnePlan

Grid Options - Gantt

Updated Oct 03, 2019

This article explains how to show the Gantt chart for your plan schedule of tasks.  You must first select Show Gantt.  Then, you may also select Show Baseline and/or Show Critical Path.

Show Gantt

Updated Header

When the Gantt is shown, three additional icons show on your header.  Click the icons to Zoom In, Zoom Out, or Scroll To (which will shift the dates to the selected task).

Previous Article Grid Options - Shared With (Build Plan Team)
Next Article Grid Options - Show Activities